Masonry

• Courtyard CMU veneer is complete
• High School CMU veneer is ongoing
• Junior High second floor interior CMU wall construction is ongoing

Structural Steel
• High School Gym mezzanine stairs are complete

Roofing
• High School roofing system installation is complete
• Board Offices & Student Dining high and low roof system installations are complete

Plumbing & Electric
• High School in-wall and overhead MEP (Mechanical Electrical Plumbing) rough-ins are complete
• High School second floor fire suppression piping rough-in is complete
• High School second floor MEP overhead rough-in is complete
• High School first and second floor overhead and in-wall MEP rough-ins are complete
• High School gymnasium overhead MEP installations are complete
• Junior High overhead MEP rough-in is ongoing
• Junior High gymnasium overhead MEP rough-ins are ongoing
• Auxiliary gymnasium overhead MEP installations are ongoing

Carpentry
• Performing Arts Center partition wall framing is ongoing
• Music rooms door and window installations are complete
• Music rooms first and second coats of paint on walls is complete
• Kitchen/Serving areas first and second coats of wall paint are complete
• Main Gymnasium first coat of paint on walls is complete
• Junior High first and second floor window unit installations are ongoing
• Junior High first and second floor interior wall framing is complete
• High School second floor insulation and drywall installations are complete
• High School first floor insulation and drywall installations are complete
• High School first and second floor window unit installations are complete
• High School second floor prime walls and first coat of paint are complete
• Junior High first and second floor window unit installation is ongoing
• Junior High first and second floors insulation and drywall Installation are ongoing