Early Site Package:

• Baseball and softball press boxes installed
• Baseball and softball bleachers installed
• Sod placed at softball field
• Baseball and softball fence pads installed
• Baseball and softball dugout benches and storage cubbies installed
• ADA ramp and steps continues
• Site concrete continues

Building Package:
Concrete
• Auxiliary gymnasium concrete slab-on-grade is complete
• Junior High area slab-on-deck concrete pour is complete
• Mechanical courtyard concrete construction is complete

Masonry
• Auxiliary gymnasium CMU is complete
• West Locker Rooms interior CMU walls are complete
• Music Rooms/BOH CMU and veneer installations is complete
• High School courtyard CMU veneer is complete
• Junior High CMU walls at first floor is complete
• High School north wall CMU veneer is ongoing
• PAC (Performing Arts Center) seating area interior CMU walls is ongoing

Structural Steel
• Music Rooms structural steel installations is complete
• Roof Decking at all gymnasiums is complete

Roofing
• Main gymnasium roofing system is complete
• PAC seating area roofing system is complete
• High School roofing system installation is ongoing
• Junior High roofing system installation is ongoing
• Music Rooms roofing system installation is ongoing
• Main Mechanical and Electrical rooms roofing systems are complete

Plumbing & Electric
• High School above ceiling MEP rough-ins is complete
• Junior High above ceiling MEP rough ins at first and second floors is ongoing

Carpentry
• Junior High interior wall framing at first and second floors is ongoing
• High School exterior and interior wall framing is complete
• Junior High exterior wall framing is complete

ConstructionUpdate11 3 21 1ConstructionUpdate11 3 21