𝐄𝐚𝐫𝐥𝐲 𝐒𝐢𝐭𝐞 𝐏𝐚𝐜𝐤𝐚𝐠𝐞
𝐒𝐨𝐟𝐭𝐛𝐚𝐥𝐥 & 𝐁𝐚𝐬𝐞𝐛𝐚𝐥𝐥 𝐅𝐢𝐞𝐥𝐝𝐬
• Concrete placed for batting cages
• Concrete placed for bleachers and press boxes
• Placement of ballfield mix
• Field irrigation system
• Outfield fencing
𝐂𝐨𝐧𝐜𝐞𝐬𝐬𝐢𝐨𝐧 𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠
• Concrete placed for sidewalks and concession stand aprons
𝐒𝐢𝐭𝐞 𝐖𝐨𝐫𝐤
• Topsoil and hydroseed placed at hillsides and soccer practice fields
• Installation of ADA ramps and stairs at hillside
𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐏𝐚𝐜𝐤𝐚𝐠𝐞
𝐂𝐨𝐧𝐜𝐫𝐞𝐭𝐞
• Completed Kitchen and Main Mechanical Rooms concrete slab on grade
• Prep for and place concrete slab on deck at Main Gymnasium south mezzanine completed
• Place concrete slab on grade at Area 4 J.H. locker areas and student areas completed
• Prep and place concrete stairs at PAC stage right and stage left ongoing
𝐌𝐚𝐬𝐨𝐧𝐫𝐲
• CMU walls at Kitchen and Main Mechanical Rooms completed
• CMU veneer at Auxiliary gymnasium east wall completed
• CMU at Auxiliary Gymnasium north and east walls completed
• CMU walls at Auxiliary Gymnasium West Locker Rooms completed
• CMU walls at South Locker Rooms completed
• CMU walls at Area One Music Rooms and Back of House areas ongoing
• CMU at JH gymnasium west and south walls ongoing
𝐒𝐭𝐫𝐮𝐜𝐭𝐮𝐫𝐚𝐥 𝐒𝐭𝐞𝐞𝐥
• Structural steel erection at Main Gymnasium south mezzanine completed
• Structural steel erection at Area 3 Administration and Special Ed first and second floors completed
• Main gymnasium north mezzanine structural steel and decking installations ongoing
𝐏𝐥𝐮𝐦𝐛𝐢𝐧𝐠 & 𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜
• MEP under slab installation at Area 4 J.H. locker areas and student areas completed
• MEP under slab installations at PAC stage area ongoing
𝐂𝐚𝐫𝐩𝐞𝐧𝐭𝐫𝐲
• Installation of treated lumber cap at PAC and Stage roof parapet walls ongoing
August 23, 2021 Update