𝐄𝐚𝐫𝐥𝐲 𝐒𝐢𝐭𝐞 𝐏𝐚𝐜𝐤𝐚𝐠𝐞
𝐂𝐨𝐧𝐜𝐞𝐬𝐬𝐢𝐨𝐧𝐬 𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠
• Beaver Construction has formed and poured the slab on grade.
• The Valentine Masonry, with assistance from the electricians and plumbing contractor, have installed the interior CMU Walls.
• Valentine Masonry has caulked all of the interior masonry control joints in preparation of interior painting.
• The Whisler Plumbing Contractor has roughed in all sanitary & domestic lines required in the mechanical chase and concessions area.
• Advance Roofing has installed the asphalt shingles.
• Carter Electric has installed the AEP Metering System.
• Carter Electric has excavated and placed all power & technology conduits from AEP.
𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜 𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠
• Advance Roofing has installed the metal roofing system.
• Valentine Masonry has caulked all of the interior masonry control joints.
𝐃𝐮𝐠𝐨𝐮𝐭𝐬
• Beaver Construction for all 4 dugouts has formed the slabs for the concrete floors.
• Valentine Masonry has caulked all of the interior masonry control joints in preparation of interior painting.
𝐒𝐨𝐟𝐭𝐛𝐚𝐥𝐥 𝐅𝐢𝐞𝐥𝐝
• Valentine Masonry has completed the knee wall between the dugouts.
𝐁𝐚𝐬𝐞𝐛𝐚𝐥𝐥 𝐅𝐢𝐞𝐥𝐝
• Valentine Masonry has completed the knee wall between the dugouts.
𝟕-𝟏𝟐 𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐏𝐚𝐜𝐤𝐚𝐠𝐞
𝐂𝐨𝐧𝐜𝐫𝐞𝐭𝐞
• All concrete foundations are now in place.
• Elevator shaft construction has begun.
• Backfill of footing ditches at Performing Arts Center (PAC) is ongoing.
𝐌𝐚𝐬𝐨𝐧𝐫𝐲
• CMU from top of footing to finish floor elevation is complete at the following areas:
• High School gymnasium perimeter
• High School gymnasium south locker room
• Auxiliary gymnasium perimeter
• Auxiliary gymnasium west locker room
• PAC walls and stage
• Music rooms
• Junior High gymnasium
• CMU from top of footing to finish floor is ongoing in the Junior High Gymnasium and Board Office areas.
• Performing Arts Center perimeter and stage CMU walls have begun.
𝐏𝐥𝐮𝐦𝐛𝐢𝐧𝐠
• Below-slab sanitary for the west locker room area is complete.
• Below-slab sanitary for the south locker room area is complete.
• Below-slab sanitary for “Area 4” Middle School is complete.
• Currently installing the underdrain piping on the north side of the Performing Arts Center.
• Currently installing the below-slab storm piping that services the building Courtyard.
• Currently installing the sanitary lines that service the Kitchen area.
• Currently laying out and roughing in In-Wall Drains for the mason.
𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜
• Below-slab and in-wall electrical conduits in the main electrical room are ongoing.
• Below-slab feeders and branch conduits from the main electrical room to various points on the project are ongoing.
• Below-slab and in-wall electrical conduits in the sub electrical rooms are ongoing.
• Working with the masons to install wall boxes and conduit as masonry walls go up.