𝐁𝐞𝐚𝐯𝐞𝐫 𝐂𝐨𝐧𝐬𝐭𝐫𝐮𝐜𝐭𝐢𝐨𝐧
• Early sitework carpenters finished the rough carpentry on the concession building roof, softball visitor’s dugout, and started the baseball visitor’s dugout.
• Building package contractors began mobilizing equipment and materials. Courtyard 8” storm line has been installed and backfilled. Rebar deliveries took place for Areas 1-6.
𝐂𝐥𝐞𝐯𝐞𝐥𝐚𝐧𝐝 𝐂𝐞𝐦𝐞𝐧𝐭
• Workers began excavation for the Performing Arts Center’s sloped floor slab.
• Excavation and installation of concrete footings has taken place for the stage and perimeter wall, Area 1 Music rooms and back-of-house.
𝐒𝐩𝐞𝐞𝐥𝐦𝐚𝐧 𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜
• Started excavation for primary underground electrical pathways from the new school transformer to the main electrical room.
• Layout of all underground conduit feeds from the main electrical room to various locations in the building has begun.
𝐒𝐭𝐚𝐧𝐝𝐚𝐫𝐝 𝐏𝐥𝐮𝐦𝐛𝐢𝐧𝐠 & 𝐇𝐞𝐚𝐭𝐢𝐧𝐠
• Layout of the underground storm and sanitary lines has begun.