𝐁𝐞𝐚𝐯𝐞𝐫 𝐂𝐨𝐧𝐬𝐭𝐫𝐮𝐜𝐭𝐢𝐨𝐧
• 𝐒𝐢𝐭𝐞𝐰𝐨𝐫𝐤 𝐂𝐫𝐞𝐰:
• Completed the storm cleanouts at the building pad
• Installed the stone construction access “Ring Road” around the new building pad
• Continued the storm piping at the south access road
• Worked with the Village Water Department and State Fire Marshall to flush & hydro test the new water supply line and fire lines for the building.
• 𝐂𝐚𝐫𝐩𝐞𝐧𝐭𝐞𝐫𝐬:
• Framed & sheathed the roofs for both the home baseball dugout & home softball dugout
• Set and braced the trusses and framed the north overhang for the concession building
𝐕𝐚𝐥𝐞𝐧𝐭𝐢𝐧𝐞 𝐌𝐚𝐬𝐨𝐧𝐫𝐲
• Completed the masonry for all 4 dugouts
• Completed the perimeter masonry for the concession building
𝐂𝐚𝐫𝐭𝐞𝐫 𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜
• Continued to work with Valentine Masonry to rough in conduits for power/lighting/fire/communication at the concession building
• Installed the buried power & technology conduits from the school transformer location to the concession transformer location
• Worked with AEP to get poles/power installed down Clever Lane to the school property
• Worked with AEP to pull primary wiring from Clever Lane to the school transformer & concession transformer locations
• Worked with AEP to set both the school & concessions transformers
• Worked with AEP to power up the new school transformer and electrical building utilizing the new primary service; The football complex is no longer powered from the school, it is now supported by the new AEP electrical service.