• Masonry on 3 of the 4 dugouts is 100% complete.
• Work on the concessions building masonry has started.
Steel
• Installation of the steel columns and roof support beams for the dugouts has started.
Site Work
• The storm piping around the new school building pad is 100% complete.
• The water line and fire hydrant loop are 100% complete.
• Fire department connection is 100% complete.
• The 8” fire & 4” domestic water line to the school building perimeter is 100% complete.
Electrical
• Below grade conduit & duct-bank from Clever Lane, through the recently installed transformer vault, to the new Electrical Building is complete.
• Electrical Building: Installation of electrical transformers, troughs, tubs, panels and controllers is 100% complete and in service
• The football complex temporary electrical cut over was successfully completed. This cut over allowed us to demolish the existing electrical building.
• The electricians have been working with the masons placing electrical conduits and boxes in/through the new masonry walls.
Demolition
• Eslich Wrecking was back on site to finish the demolition scope of the project. The work performed was demolition of the original electrical building. The demolition scope is now 100% Complete.
January 6, 2021 Update