𝐂𝐚𝐫𝐭𝐞𝐫 𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜
• Has installed the Electrical Duct Bank from Clever Lane to the location of the new AEP Transformer.
• They have started the rough in of the Electrical Equipment in the new Electrical Building. The new equipment in this Electrical Building will service the Football Stadium, Maintenance Areas and Field House.
• Has installed the below slab conduits at the Concessions Building.
• Working with AEP to bring new Electrical Service Down Clever Lane to the School Property.
• Working with Valentine Masonry to Rough in Conduits in the Masonry Walls.
𝐖𝐡𝐢𝐬𝐥𝐞𝐫 𝐏𝐥𝐮𝐦𝐛𝐢𝐧𝐠 & 𝐇𝐞𝐚𝐭𝐢𝐧𝐠
• Whisler has installed all of the below slab plumbing and irrigation lines in the Concession Building.
𝐕𝐚𝐥𝐞𝐧𝐭𝐢𝐧𝐞 𝐌𝐚𝐬𝐨𝐧𝐫𝐲
• Has laid up enough block to bring the Concessions Building 2 courses above grade
• Softball Visitor Dugout is 100% Complete
• Baseball Visitor Dugout is 100% Complete
• The Softball & Baseball Knee Walls are in progress
• The Baseball Home Dugout is in progress
• The Softball Home Dugout has 1 course of block laid and will continue this week.
𝐁𝐞𝐚𝐯𝐞𝐫 𝐄𝐱𝐜𝐚𝐯𝐚𝐭𝐨𝐫𝐬
• Sanitary Line is 100%
• Storm Lines are approximately 80%
• New Water Line is approximately 55%
• New School Building Pad is to Grade