Lexington families welcomed students and teachers from Costa Rica! They had an amazing time experiencing our cultureโ€”and for many, seeing snow and feeling cold temperatures for the first time! What a memorable exchange!

Mr. Hoffman and his Studio Jewelry students took a field trip to Rego Jewelers in Bucyrus to see large-scale jewelry manufacturing in action! With 50 employees and an annual revenue of $10โ€“$12 million, Rego Jewelers gave students an inside look at the industry. They also ...

Valentineโ€™s Day was extra special at Eastern, thanks to a group of kindhearted girls who gave up their recess to create over 500 heart-shaped pins for every student and staff member! Their generosity made the day even more meaningful!

Members of the High School Leadership Council attended a Leadership Conference at Wooster High School. They shared their community outreach efforts with fellow OCC schools and took part in interactive leadership activities with other OCC athletes. A great day of growth ...

Centralโ€™s annual 3rd Grade Spelling Bee was a great success! Congratulations to Keith R., this yearโ€™s champion! Way to go, Keith, and to all the students who participatedโ€”you made us proud!

 Congratulations to Logan B., who had the incredible honor of performing with the Ohio All-State Orchestra in Cleveland on Friday, February 7. What an amazing achievement!

Central students had a fantastic time on their field trip to the Mansfield Symphony Orchestra for the "Link Up: The Orchestra Rocks" concert at the Renaissance Theater. They enjoyed the live music and discovered the power of the orchestra!

First graders at Western celebrated the 100th day of school with tons of counting activities, building their math skills while having fun. What a great way to mark this milestone!



Congratulations to the 6th grade and JH Mathcounts teams who competed at Ashland University. 6th grade team: Ben C, Monte C, Grayson W, Conner D JH team: Ebube E, Elijah E, Emma E, Marissa R, Harrison R Special congrats to Ebube E and Elijah E who made the top 10 in ...



Congratulations to the 5th grade academic challenge teams who took 5th and 6th out of 34 teams. Teams consisted of Violet H., Jax E., Robbie S., Nolan H. and Noah B., Ben T., and Addy M.

Eastern's 6th grade Academic Challenge took 1st place out of 32 teams at their meet on Jan. 28th. The first place team consisted of Ben M., Monte C., Ina G., and Emily S.

Sixth graders in Mrs. Smith's science classes had fun using the Ohio Energy activities. They learned about energy conservation and energy usage.

Great job to our Eastern Spelling Bee participants: Charlie P., Caden L., Peyton F., and Addy M. Special congrats and good luck to Addy and Caden, who made the top 18 in Richland County and are headed to the Tri-County Bee!

A new semester means new robots in the STEM Lab! Under Mr. Deweyโ€™s guidance, 8th-grade students have been busy building Vex IQ base bots to tackle their first STEM challenge: navigating an obstacle course. They were all excellent bot navigators!

Do you want to build a snowman? Mrs. Lohrโ€™s class did a fantastic job using life-size snowmen to show their winter stories' beginning, middle, and end. Keep up the great work!

Before winter break, Easternโ€™s Military Kids collected and delivered gifts to nursing home residents at Lexington Court Care Center, and they were so appreciative of each gift! It is nice to make their holidays a little brighter!

Kyland and Mrs. Galbraith had a fantastic day of learning at Central, where building strong relationships is always a top priority!

Congratulations to the string students who performed at Region Orchestra at Ashland High School. Great job, Owen G., Logan B., Ben W., Emma T., Annie H., Sylvia S., Alexis F., and Iris P. We are proud of you!

Congratulations to Addy B., Lexington junior, who has been selected as the Pioneer Career & Technology Centerโ€™s December Student of the Month. Keep up the great work, Addy!

Students in Dr. Berryโ€™s math class used the book "Picture Pie" as inspiration to make pictures entirely out of circles and fractions of circles. They then had to add fractions, find ratios to compare them, and convert them to decimals and percents!

Third-grade students at Central read three versions of โ€œStone Soup,โ€ compared and contrasted versions, and discussed the morals of kindness, generosity, and gratitude. Then, each student brought in an ingredient, and together, they created 'stone soup' and enjoyed a ...

The students at Eastern love when Mr. Grist stops in the art room, and Mrs. Haas seldom lets him leave without creating something with them. On his last visit, they drew self-portraits. Thanks for creating with them, Mr. Grist!

Lex Leadership Council members had an unforgettable experience at the MOESC Leadership Conference, where they heard an inspiring presentation from former Ohio State and NFL wide receiver, Roy Hall Jr.! Thank you, Mr. Hall, for motivating our future leaders!

Western Elementary proudly celebrated our military kids and their families on Friday with a breakfast in their honor. It was a special time to show gratitude for their service and the sacrifices they make for our country. We are so grateful for each of them!

Mrs. Coffmanโ€™s third-grade class at Central Elementary participated in a mock election during a social studies lesson on local government. Students ran for mayor or city council, and citizens voted. Town meetings were held to determine laws, building designs, and names. ...

Ms. Blackstone and Mrs. Hughes celebrated National STEM Day by giving their 2nd and 3rd graders a unique milk-tasting STEM experience! Students tasted strawberry, regular, and chocolate milk, created and analyzed data graphs, and wrote opinion paragraphs. Both classes are ...

Dr. Berryโ€™s sixth-grade class had a Glow Day review for their upcoming test! Students rotated through stations focused on dividing fractions, GCF, LCM, coordinate planes, division, and decimal operations. This review truly brightened their day!

Check out these moments from our 1st Quarter PBIS Celebration at Central Elementary! Our students had a great time celebrating their positive behavior and achievements. Congratulations to all!

Military Kids at Western Elementary had a blast with some Halloween fun! Students made creative masks and enjoyed delicious treats. They had spook-tacular time!

Mrs. Winner's kindergarten students celebrated learning the letters "p" and "j" by making and eating peanut butter and jelly sandwiches. They then wrote directions to help others enjoy this tasty treat!

Visitors From Costa Rica
Visitors From Costa Rica
Studio Jewelry Field Trip
Studio Jewelry Field Trip
Valentine's Day Heart Pins
Valentine's Day Heart Pins
High School Leadership Council
High School Leadership Council
Central Spelling Bee
Central Spelling Bee
Ohio All State Orchestra
Ohio All State Orchestra
Renaissance Theater Field Trip
Renaissance Theater Field Trip
First Graders Celebrate 100th Day
First Graders Celebrate 100th Day
MathCounts Teams
MathCounts Teams
5th Grade Academic Challenge Team
5th Grade Academic Challenge Team
6th Grade Academic Challenge Team
6th Grade Academic Challenge Team
Ohio Energy Activities
Ohio Energy Activities
Eastern Spelling Bee
Eastern Spelling Bee
Mr. Dewey's Robotic Classes
Mr. Dewey's Robotic Classes
Do You Want to Build a Snowman?
Do You Want to Build a Snowman?
Delivering Gifts to Nursing Home
Delivering Gifts to Nursing Home
Kyland and Mrs. Galbraith
Kyland and Mrs. Galbraith
Region Orchestra
Region Orchestra
Pioneer December Student of the Month
Pioneer December Student of the Month
Picture Pie
Picture Pie
Stone Soup
Stone Soup
Mr. Grist Self Portrait
Mr. Grist Self Portrait
Lex Leadership Council
Lex Leadership Council
Veterans Day Breakfast
Veterans Day Breakfast
Mock Election
Mock Election
National STEM Day
National STEM Day
Glow Day Review
Glow Day Review
Central's 1st Quarter PBIS Celebration
Central's 1st Quarter PBIS Celebration
Military Kids Halloween Fun!
Military Kids Halloween Fun!
Peanut Butter and Jelly
Peanut Butter and Jelly

Carpentry


โ€ข Music rooms casework installations completed
โ€ข Music rooms acoustic wall panels completed
โ€ข PAC stage flooring ongoing
โ€ขPAC ceiling finishes ongoing
โ€ข PAC acoustic wall panels ongoing
โ€ข West locker rooms flooring and ceiling tile installations completed
โ€ข Main Gymnasium flooring installation ongoing
โ€ข Kitchen corridors and support spaces ceiling tile installation ongoing
โ€ข High School & Junior High main entrance steel canopies completed
โ€ข Board Office areas flooring installation completed
โ€ข Board Office casework installation ongoing
โ€ข Student dining area ceiling grid installation ongoing
โ€ข JH locker rooms flooring and ceiling grid installations completed
โ€ข Junior High first floor ceiling grid and tile completed
โ€ข Junior High second floor flooring and ceiling tile installations completed
โ€ข Junior High first floor flooring installation ongoing
โ€ข High School first and second floors commons area flooring completed
โ€ข Junior High first floor ceiling grid and MEP finishes completed
โ€ข Junior High first floor ceiling tile installation completed
โ€ข Junior High second floor ceiling tile installations completed
โ€ข Junior High second floor flooring installation completed
โ€ข Junior High first floor flooring installation ongoing
โ€ข Junior High first floor casework installation ongoing
โ€ข Junior High second floor casework installation ongoing

Misc. Finishes

โ€ข Furniture deliveries ongoing
โ€ข High School first floor classroom furniture setup completed
โ€ข High School second floor classroom furniture set up completed
โ€ข Kitchen equipment installations ongoing

Concrete & Courtyard area

โ€ข Sitework concrete and pavement installations completed
โ€ข Student courtyard decorative gravel installation completed

Mechanical, Plumbing & Electric

โ€ข HVAC start-ups completed
โ€ข Student dining areas above ceiling MEP rough-ins completed

July22ConstructionUpdate

Carpentry

โ€ข Student Courtyard Concrete Installation completed
โ€ข Junior High Second Floor Ceiling Grid completed
โ€ข High School First and Second Floor Casework Installations completed
โ€ข Junior High First and Second Floor Ceiling Grid Installations completed
โ€ข Kitchen/Serving Areas Ceiling Grid Installation completed
โ€ข Kitchen/Serving Areas Ceiling Grid Installation completed
โ€ข Music Rooms Casework Installations ongoing
โ€ข PAC Ceiling Finishes ongoing
โ€ข Music Rooms Acoustic Wall Panels ongoing
โ€ข Junior High First Floor Ceiling Grid ongoing
โ€ข Junior High Second Floor Ceiling Tile Installations ongoing

Misc. Finishes

โ€ข Kitchen Serving Areas Epoxy Flooring Installation completed
โ€ข Main Gymnasium Gym Equipment Installations completed
โ€ข South Locker Rooms Flooring Installation completed
โ€ข Kitchen Serving Areas Epoxy Flooring Installation completed
โ€ข Main Gymnasium Gym Equipment Installations completed
โ€ข Elevator and Wheelchair Lift Installations completed
โ€ข Board of Education First and Second Floor Porcelain Tile at Bathrooms completed
โ€ข Board of Education Office Areas Ceiling Grid and Tile Installations completed
โ€ข Furniture Deliveries ongoing
โ€ข PAC Stage Flooring ongoing
โ€ข West Locker Rooms Flooring Installations ongoing
โ€ข High School & Junior High Main Entrance Steel Canopies ongoing
โ€ข High School First and Second Floors Commons Area Flooring ongoing

Concrete & Courtyard area

โ€ข Student Dining Stairs Installation and Concrete Infill completed
โ€ข Site Concrete sidewalks and pavement Installations ongoing
โ€ข Student Courtyard Decorative Gravel Installation ongoing

Plumbing & Electric

โ€ข Main Gymnasium Overhead MEP Installations completed
โ€ข South and West Locker Rooms Plumbing Fixture Installations completed
โ€ข Junior High First and Second Floor Above Ceiling MEP Rough Ins completed
โ€ข Student Dining Areas Above Ceiling MEP Rough Ins ongoing
โ€ข Junior High First Floor MEP Finishes ongoing

June22Construction

Carpentry

โ€ข Performing Arts Center (PAC) stage area rigging and equipment installation completed
โ€ข Elevator installation ongoing
โ€ข PAC back of house and music rooms ceiling grid completed
โ€ข High School and Auxiliary locker rooms ceiling grid installations completed
โ€ข High School main entrance exterior wall framing completed
โ€ข Board Office and first floor ceiling grid installations completed
โ€ข High School second floor drywall finishing completed
โ€ข Junior High first floor hang drywall completed
โ€ข Junior High first floor finish drywall completed
โ€ข High School first floor ceiling grid completed
โ€ข Junior High second floor ceiling grid completed
โ€ข Junior High first floor ceiling grid completed
โ€ข Kitchen/Serving areas ceiling grid installation ongoing
โ€ข Junior High first and second floor ceiling grid installations ongoing

Misc. Finishes

โ€ข High School second floor wall painting completed
โ€ข Junior High first floor wall painting completed
โ€ข Junior High locker rooms wall painting ongoing
โ€ข High School first floor classroom flooring completed
โ€ข Junior High gymnasium wood flooring installation ongoing
โ€ข High School gymnasium equipment installations ongoing
โ€ข Board Offices & High School first and second floor porcelain tile at bathrooms ongoing
โ€ข Junior High first and second floor porcelain tile at bathrooms ongoing

Masonry/Concrete

โ€ข Sitework concrete and pavement installations ongoing
โ€ข Student courtyard concrete installation ongoing
โ€ข High School entrance CMU veneer completed
โ€ข Junior High exterior CMU veneer completed

Plumbing & Electric

โ€ข Kitchen fume hoods and ductwork installations completed
โ€ข Junior High first and second floor above ceiling MEP rough-ins ongoing

ConstructionUpdateMay22                                          

 

Masonry

โ€ข Courtyard CMU veneer is complete
โ€ข High School CMU veneer is ongoing
โ€ข Junior High second floor interior CMU wall construction is ongoing

Structural Steel
โ€ข High School Gym mezzanine stairs are complete

Roofing
โ€ข High School roofing system installation is complete
โ€ข Board Offices & Student Dining high and low roof system installations are complete

Plumbing & Electric
โ€ข High School in-wall and overhead MEP (Mechanical Electrical Plumbing) rough-ins are complete
โ€ข High School second floor fire suppression piping rough-in is complete
โ€ข High School second floor MEP overhead rough-in is complete
โ€ข High School first and second floor overhead and in-wall MEP rough-ins are complete
โ€ข High School gymnasium overhead MEP installations are complete
โ€ข Junior High overhead MEP rough-in is ongoing
โ€ข Junior High gymnasium overhead MEP rough-ins are ongoing
โ€ข Auxiliary gymnasium overhead MEP installations are ongoing

Carpentry
โ€ข Performing Arts Center partition wall framing is ongoing
โ€ข Music rooms door and window installations are complete
โ€ข Music rooms first and second coats of paint on walls is complete
โ€ข Kitchen/Serving areas first and second coats of wall paint are complete
โ€ข Main Gymnasium first coat of paint on walls is complete
โ€ข Junior High first and second floor window unit installations are ongoing
โ€ข Junior High first and second floor interior wall framing is complete
โ€ข High School second floor insulation and drywall installations are complete
โ€ข High School first floor insulation and drywall installations are complete
โ€ข High School first and second floor window unit installations are complete
โ€ข High School second floor prime walls and first coat of paint are complete
โ€ข Junior High first and second floor window unit installation is ongoing
โ€ข Junior High first and second floors insulation and drywall Installation are ongoing

ConstructionUpdate2 22

Concrete

โ€ข Junior High second story concrete floor pour is complete

Masonry
โ€ข Junior High east wall CMU veneer is complete
โ€ข Junior High second floor interior CMU wall construction ongoing
โ€ข High School and Junior High east wall brick veneer ongoing

Structural Steel
โ€ข Student Dining Area structural steel installation is complete
โ€ข Student Dining Area structural steel and decking installations is complete

Roofing
โ€ข Music Rooms roof detailing is complete
โ€ข Junior High roof detailing is complete
โ€ข Junior High Gymnasium roof detailing is complete
โ€ข High School Gymnasium roof detailing is complete
โ€ข Auxiliary Gymnasium roof detailing is complete
โ€ข Junior High roofing system installation ongoing
โ€ข Board Offices high and low roof system installations ongoing

Plumbing & Electric
โ€ข Gas service to the building is complete
โ€ข High School first and second floor in-wall mechanical, electrical, and plumbing (MEP) rough-ins are complete
โ€ข High School first and second floor overhead and in-wall MEP rough-ins ongoing
โ€ข Junior High Air Handling Unit installations are complete
โ€ข Rooftop HVAC unit installations are complete
โ€ข Electric service to the building is complete
โ€ข Junior High in-wall and overhead MEP rough-ins ongoing
โ€ข Junior High gymnasium overhead MEP rough-ins ongoing
โ€ข Main gymnasium overhead MEP installations ongoing
โ€ข Auxiliary gymnasium overhead MEP installations ongoing

Carpentry
โ€ข Junior High window installations is complete
โ€ข Junior High exterior wall framing is complete
โ€ข High School second floor insulation and drywall installations ongoing
โ€ข Music rooms doors and windows installations ongoing
โ€ข Performing Arts Center partition wall framing ongoing

ConstructionUpdateJan2022

Early Site Package:

โ€ข ADA ramp to baseball field concrete work was completed
โ€ข Baseball field sod placement is nearing completion
โ€ข Bleachers & press boxes were completed for both the softball and baseball fields
โ€ข The asphalt drive to the baseball field was completed
โ€ข The cubbies in all dugouts were completed
โ€ข The net systems for the batting cages was completed
โ€ข Final grade and seed are in progress

Building Package:
Masonry
โ€ข Courtyard CMU veneer is complete
โ€ข Performing Arts Center seating area interior CMU walls is complete
โ€ข Music Rooms non-bearing interior CMU walls is complete
โ€ข South Locker Rooms non-bearing interior CMU walls is complete
โ€ข West Locker Rooms non-bearing interior CMU walls is complete
โ€ข High School (HS) north wall CMU veneer ongoing
โ€ข Junior High (JH) east wall CMU veneer ongoing

Structural Steel
โ€ข JH structural steel and decking installations are complete
โ€ข Dining area structural steel installation ongoing

Roofing
โ€ข HS roofing system installation is complete
โ€ข Music Rooms roofing system installation is complete
โ€ข Main Gym/North and South Mezzanines roofing system installation is complete
โ€ข JH Gym roofing system installation is complete
โ€ข Auxiliary Gym roofing system installation is complete
โ€ข Main Mechanical and Electrical Rooms roofing system installation is complete
โ€ข Area 3 roofing system installation ongoing

Plumbing & Electric
โ€ข JH above ceiling mechanical, electrical, and plumbing (MEP) rough-ins at first and second floors are complete
โ€ข Main Gym Overhead MEP rough-ins ongoing
โ€ข JH first and second floor overhead MEP rough-ins ongoing
โ€ข JH first and second floor in wall MEP rough-ins ongoing
โ€ข HS first and second floor in wall MEP rough-ins ongoing

Carpentry
โ€ข HS interior wall framing at first and second floors is complete
โ€ข HS exterior wall framing is complete
โ€ข HS and JH window system installations ongoing

ConstructionUpdate12 3 21 1ConstructionUpdate12 3 21 2

Early Site Package:

โ€ข Baseball and softball press boxes installed
โ€ข Baseball and softball bleachers installed
โ€ข Sod placed at softball field
โ€ข Baseball and softball fence pads installed
โ€ข Baseball and softball dugout benches and storage cubbies installed
โ€ข ADA ramp and steps continues
โ€ข Site concrete continues

Building Package:
Concrete
โ€ข Auxiliary gymnasium concrete slab-on-grade is complete
โ€ข Junior High area slab-on-deck concrete pour is complete
โ€ข Mechanical courtyard concrete construction is complete

Masonry
โ€ข Auxiliary gymnasium CMU is complete
โ€ข West Locker Rooms interior CMU walls are complete
โ€ข Music Rooms/BOH CMU and veneer installations is complete
โ€ข High School courtyard CMU veneer is complete
โ€ข Junior High CMU walls at first floor is complete
โ€ข High School north wall CMU veneer is ongoing
โ€ข PAC (Performing Arts Center) seating area interior CMU walls is ongoing

Structural Steel
โ€ข Music Rooms structural steel installations is complete
โ€ข Roof Decking at all gymnasiums is complete

Roofing
โ€ข Main gymnasium roofing system is complete
โ€ข PAC seating area roofing system is complete
โ€ข High School roofing system installation is ongoing
โ€ข Junior High roofing system installation is ongoing
โ€ข Music Rooms roofing system installation is ongoing
โ€ข Main Mechanical and Electrical rooms roofing systems are complete

Plumbing & Electric
โ€ข High School above ceiling MEP rough-ins is complete
โ€ข Junior High above ceiling MEP rough ins at first and second floors is ongoing

Carpentry
โ€ข Junior High interior wall framing at first and second floors is ongoing
โ€ข High School exterior and interior wall framing is complete
โ€ข Junior High exterior wall framing is complete

ConstructionUpdate11 3 21 1ConstructionUpdate11 3 21

Early Site Package:

Baseball & Softball Fields
โ€ข Foul ball poles have been installed on both fields
โ€ข Scoreboards for both fields have been installed
โ€ข Benches in the dugouts are currently being installed
โ€ข Both fields have been prepped and for sod
โ€ข Sod installation began week of 9/27
โ€ข Irrigation systems will be final tested this week
โ€ข Press boxes have been delivered

ADA Access Ramp
โ€ข The ADA Ramp is progressing. Beaver continues to form and pour sections of the walls. Once the walls are done they will start the stair sections and slabs on grade.

Building Package:
Concrete
โ€ข Area 5 second floor concrete slab placement completed
โ€ข JH gymnasium concrete slab on grade placement completed
โ€ข Main gymnasium concrete slab on grade placement completed

Masonry
โ€ข Main gymnasium CMU veneer at exterior walls completed
โ€ข JH gymnasium CMU veneer at exterior walls completed
โ€ข Music rooms CMU and brick veneer installations ongoing

Structural Steel
โ€ข In-wall MEP rough-in at Area 3 board office partition walls completed
โ€ข Area 5 structural steel and decking installation completed
โ€ข Area 6 structural steel installation completed
โ€ข JH gymnasium steel bar joist installations completed
โ€ข Main gymnasium steel bar joist installations completed
โ€ข Auxiliary gymnasium steel bar joist installations completed
โ€ข Main mechanical and main electrical rooms steel bar joist and decking installations completed
โ€ข Area 6 structural roof decking installations ongoing
โ€ข Main gym/JH gym/Auxiliary gym structural roof decking installations ongoing
โ€ข Music rooms structural steel roof bar joist and roof decking installations

Roofing
โ€ข West locker rooms roof system installation completed
โ€ข Performing Arts Center stage area roof system installation completed
โ€ข Performing Arts Center seating area roof system installation completed

Plumbing & Electric
โ€ข South Locker Rooms above-ceiling MEP rough-in completed
โ€ข Kitchen and Serving Areas above ceiling MEP installations ongoing
โ€ข Area 3 above ceiling MEP rough ins ongoing
โ€ข Area 5 above ceiling MEP rough ins ongoing

Carpentry
โ€ข Exterior and interior wall framing at Area 3 board offices completed
โ€ข Area 5 interior and exterior wall framing ongoing

ConstructionSept21 1ConstructionSept21 2

๐„๐š๐ซ๐ฅ๐ฒ ๐’๐ข๐ญ๐ž ๐๐š๐œ๐ค๐š๐ ๐ž

๐’๐จ๐Ÿ๐ญ๐›๐š๐ฅ๐ฅ & ๐๐š๐ฌ๐ž๐›๐š๐ฅ๐ฅ ๐…๐ข๐ž๐ฅ๐๐ฌ
โ€ข Concrete placed for batting cages
โ€ข Concrete placed for bleachers and press boxes
โ€ข Placement of ballfield mix
โ€ข Field irrigation system
โ€ข Outfield fencing
๐‚๐จ๐ง๐œ๐ž๐ฌ๐ฌ๐ข๐จ๐ง ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
โ€ข Concrete placed for sidewalks and concession stand aprons
๐’๐ข๐ญ๐ž ๐–๐จ๐ซ๐ค
โ€ข Topsoil and hydroseed placed at hillsides and soccer practice fields
โ€ข Installation of ADA ramps and stairs at hillside

๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐  ๐๐š๐œ๐ค๐š๐ ๐ž

๐‚๐จ๐ง๐œ๐ซ๐ž๐ญ๐ž
โ€ข Completed Kitchen and Main Mechanical Rooms concrete slab on grade
โ€ข Prep for and place concrete slab on deck at Main Gymnasium south mezzanine completed
โ€ข Place concrete slab on grade at Area 4 J.H. locker areas and student areas completed
โ€ข Prep and place concrete stairs at PAC stage right and stage left ongoing
๐Œ๐š๐ฌ๐จ๐ง๐ซ๐ฒ
โ€ข CMU walls at Kitchen and Main Mechanical Rooms completed
โ€ข CMU veneer at Auxiliary gymnasium east wall completed
โ€ข CMU at Auxiliary Gymnasium north and east walls completed
โ€ข CMU walls at Auxiliary Gymnasium West Locker Rooms completed
โ€ข CMU walls at South Locker Rooms completed
โ€ข CMU walls at Area One Music Rooms and Back of House areas ongoing
โ€ข CMU at JH gymnasium west and south walls ongoing
๐’๐ญ๐ซ๐ฎ๐œ๐ญ๐ฎ๐ซ๐š๐ฅ ๐’๐ญ๐ž๐ž๐ฅ
โ€ข Structural steel erection at Main Gymnasium south mezzanine completed
โ€ข Structural steel erection at Area 3 Administration and Special Ed first and second floors completed
โ€ข Main gymnasium north mezzanine structural steel and decking installations ongoing
๐๐ฅ๐ฎ๐ฆ๐›๐ข๐ง๐  & ๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ
โ€ข MEP under slab installation at Area 4 J.H. locker areas and student areas completed
โ€ข MEP under slab installations at PAC stage area ongoing
๐‚๐š๐ซ๐ฉ๐ž๐ง๐ญ๐ซ๐ฒ
โ€ข Installation of treated lumber cap at PAC and Stage roof parapet walls ongoing

Side1
Side2
Side3
Side4

๐„๐š๐ซ๐ฅ๐ฒ ๐’๐ข๐ญ๐ž ๐๐š๐œ๐ค๐š๐ ๐ž
๐‚๐จ๐ง๐œ๐ž๐ฌ๐ฌ๐ข๐จ๐ง๐ฌ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
โ€ข Above ceiling electrical rough-in has been completed.
โ€ข The electrical room panels and transformer have been installed and wired.
โ€ข Lighting suspended in the acoustic grid and has been installed.
โ€ข Above ceiling mechanical has been completed.
โ€ข Toilet chase rough-in and above ceiling rough-in has been completed.
โ€ข Interior walls have been cleaned and painted.
โ€ข Drywall ceilings have been hung.
โ€ข Acoustical ceiling grid has been laid out and installed.
โ€ข Concrete frost slabs have been poured.
โ€ข Irrigation system supply piping is being installed.
๐ƒ๐ฎ๐ ๐จ๐ฎ๐ญ๐ฌ
โ€ข Metal roofing, trim & downspouts are nearing completion.
โ€ข Masonry has been painted.
โ€ข Concrete slabs/frost slabs have been poured.
โ€ข Doors and hardware have been installed.
๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ๐š๐ฅ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
โ€ข Metal roofing, trim & downspout are nearing completion.
โ€ข Concrete frost slab was poured.
โ€ข Door opening is being prepped for door and hardware placement.
๐’๐ข๐ญ๐ž๐ฐ๐จ๐ซ๐ค
โ€ข All storm piping has been completed.
โ€ข Storm structure inverts have been poured.
โ€ข The Bio-Retention pond at 546 has been excavated and media has been placed.
โ€ข Fine grade and topsoil have been placed on the south side of the property, around the detention pond and on the majority of the soccer fields.
โ€ข Grass seed is placed on the south side of the property and around the detention pond. Seed placement will continue north towards the new school building.
โ€ข The fire lane on the east side of the new school has been cut to grade and stoned.
โ€ข Installation of site conduits from the concession building to the dugouts, scoreboards, and future ball field lighting is in progress.

๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐  ๐๐š๐œ๐ค๐š๐ ๐ž
๐‚๐จ๐ง๐œ๐ซ๐ž๐ญ๐ž
โ€ข Elevator shaft foundations/pit slab and pit walls are complete.
โ€ข SOG prep and pour at Area 3 (admin) area is ongoing.
โ€ข SOG prep at Area 5 (high school academic) area is ongoing.
๐Œ๐š๐ฌ๐จ๐ง๐ซ๐ฒ
โ€ข CMU at PAC/stage north and west walls are complete.
โ€ข CMU from top of footing to FF elevation at entire perimeter of building is complete.
โ€ข Structural steel column base plates and grout is complete.
โ€ข CMU to roof height at Area 2 main electrical room is complete.
โ€ข Masonry veneer at PAC/stage north and west walls is ongoing.
โ€ข CMU at PAC/stage south wall is ongoing.
โ€ข CMU at main gymnasium walls is ongoing.
โ€ข CMU at JH gymnasium north and east walls is ongoing.
๐๐ฅ๐ฎ๐ฆ๐›๐ข๐ง๐ 
โ€ข Standard Plumbing has continued with the below slab installation of the sanitary lines, storm lines and acid waste lines in the Administration area, the kitchen, and education areas.
โ€ข Standard Plumbing has been working with Valentine Masonry coordinating all wall sleeves for future pipe installations and all wall openings for future duct installation.
๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ
โ€ข Speelman Electric has continued with the below slab installation of the feeder conduits from the main electrical rooms to sub locations and then all of the branch circuits for distribution.
โ€ข Speelman Electric has been working with Valentine Masonry coordinating all of the in- wall conduits for lighting, power, equipment, etc. as required.
โ€ข Speelman Electric has excavated, placed and backfilled site electrical conduits from the main building down the access road to Route 546. They have placed the light pole bases down the access road to Route 546.

Construction6.14 1
Construction6.14

๐„๐š๐ซ๐ฅ๐ฒ ๐’๐ข๐ญ๐ž ๐๐š๐œ๐ค๐š๐ ๐ž

๐‚๐จ๐ง๐œ๐ž๐ฌ๐ฌ๐ข๐จ๐ง๐ฌ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
โ€ข Above ceiling electrical rough-in has been completed.
โ€ข The electrical room panels and transformer have been installed and wired.
โ€ข Lighting suspended in the acoustic grid and has been installed.
โ€ข Above ceiling mechanical has been completed.
โ€ข Toilet chase rough-in and above ceiling rough-in has been completed.
โ€ข Interior walls have been cleaned and painted.
โ€ข Drywall ceilings have been hung.
โ€ข Acoustical ceiling grid has been laid out and installed.
โ€ข Concrete frost slabs have been poured.
โ€ข Irrigation system supply piping is being installed.

๐ƒ๐ฎ๐ ๐จ๐ฎ๐ญ๐ฌ
โ€ข Metal roofing, trim & downspouts are nearing completion.
โ€ข Masonry has been painted.
โ€ข Concrete slabs/frost slabs have been poured.
โ€ข Doors and hardware have been installed.

๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ๐š๐ฅ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
โ€ข Metal roofing, trim & downspout are nearing completion.
โ€ข Concrete frost slab was poured.
โ€ข Door opening is being prepped for door and hardware placement.

๐’๐ข๐ญ๐ž๐ฐ๐จ๐ซ๐ค
โ€ข All storm piping has been completed.
โ€ข Storm structure inverts have been poured.
โ€ข The Bio-Retention pond at 546 has been excavated and media has been placed.
โ€ข Fine grade and topsoil have been placed on the south side of the property, around the detention pond and on the majority of the soccer fields.
โ€ข Grass seed is placed on the south side of the property and around the detention pond. Seed placement will continue north towards the new school building.
โ€ข The fire lane on the east side of the new school has been cut to grade and stoned.
โ€ข Installation of site conduits from the concession building to the dugouts, scoreboards, and future ball field lighting is in progress.

๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐  ๐๐š๐œ๐ค๐š๐ ๐ž

๐‚๐จ๐ง๐œ๐ซ๐ž๐ญ๐ž
โ€ข Elevator shaft foundations/pit slab and pit walls are complete.
โ€ข SOG prep and pour at Area 3 (admin) area is ongoing.
โ€ข SOG prep at Area 5 (high school academic) area is ongoing.

๐Œ๐š๐ฌ๐จ๐ง๐ซ๐ฒ
โ€ข CMU at PAC/stage north and west walls are complete.
โ€ข CMU from top of footing to FF elevation at entire perimeter of building is complete.
โ€ข Structural steel column base plates and grout is complete.
โ€ข CMU to roof height at Area 2 main electrical room is complete.
โ€ข Masonry veneer at PAC/stage north and west walls is ongoing.
โ€ข CMU at PAC/stage south wall is ongoing.
โ€ข CMU at main gymnasium walls is ongoing.
โ€ข CMU at JH gymnasium north and east walls is ongoing.
 
๐๐ฅ๐ฎ๐ฆ๐›๐ข๐ง๐ 
โ€ข Standard Plumbing has continued with the below slab installation of the sanitary lines, storm lines and acid waste lines in the Administration area, the kitchen, and education areas.
โ€ข Standard Plumbing has been working with Valentine Masonry coordinating all wall sleeves for future pipe installations and all wall openings for future duct installation.
 
๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ
โ€ข Speelman Electric has continued with the below slab installation of the feeder conduits from the main electrical rooms to sub locations and then all of the branch circuits for distribution.
โ€ข Speelman Electric has been working with Valentine Masonry coordinating all of the in- wall conduits for lighting, power, equipment, etc. as required.
โ€ข Speelman Electric has excavated, placed and backfilled site electrical conduits from the main building down the access road to Route 546. They have placed the light pole bases down the access road to Route 546.
 
ConstructionUpdate5.6.21
ConstructionUpdate5.6.21 1

๐„๐š๐ซ๐ฅ๐ฒ ๐’๐ข๐ญ๐ž ๐๐š๐œ๐ค๐š๐ ๐ž

๐‚๐จ๐ง๐œ๐ž๐ฌ๐ฌ๐ข๐จ๐ง๐ฌ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
โ€ข Beaver Construction has formed and poured the slab on grade.
โ€ข The Valentine Masonry, with assistance from the electricians and plumbing contractor, have installed the interior CMU Walls.
โ€ข Valentine Masonry has caulked all of the interior masonry control joints in preparation of interior painting.
โ€ข The Whisler Plumbing Contractor has roughed in all sanitary & domestic lines required in the mechanical chase and concessions area.
โ€ข Advance Roofing has installed the asphalt shingles.
โ€ข Carter Electric has installed the AEP Metering System.
โ€ข Carter Electric has excavated and placed all power & technology conduits from AEP.

๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
โ€ข Advance Roofing has installed the metal roofing system.
โ€ข Valentine Masonry has caulked all of the interior masonry control joints.

๐ƒ๐ฎ๐ ๐จ๐ฎ๐ญ๐ฌ
โ€ข Beaver Construction for all 4 dugouts has formed the slabs for the concrete floors.
โ€ข Valentine Masonry has caulked all of the interior masonry control joints in preparation of interior painting.

๐’๐จ๐Ÿ๐ญ๐›๐š๐ฅ๐ฅ ๐…๐ข๐ž๐ฅ๐
โ€ข Valentine Masonry has completed the knee wall between the dugouts.

๐๐š๐ฌ๐ž๐›๐š๐ฅ๐ฅ ๐…๐ข๐ž๐ฅ๐
โ€ข Valentine Masonry has completed the knee wall between the dugouts.

๐Ÿ•-๐Ÿ๐Ÿ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐  ๐๐š๐œ๐ค๐š๐ ๐ž

๐‚๐จ๐ง๐œ๐ซ๐ž๐ญ๐ž
โ€ข All concrete foundations are now in place.
โ€ข Elevator shaft construction has begun.
โ€ข Backfill of footing ditches at Performing Arts Center (PAC) is ongoing.

๐Œ๐š๐ฌ๐จ๐ง๐ซ๐ฒ
โ€ข CMU from top of footing to finish floor elevation is complete at the following areas:
    โ€ข High School gymnasium perimeter
    โ€ข High School gymnasium south locker room
    โ€ข Auxiliary gymnasium perimeter
    โ€ข Auxiliary gymnasium west locker room
    โ€ข PAC walls and stage
    โ€ข Music rooms
    โ€ข Junior High gymnasium
โ€ข CMU from top of footing to finish floor is ongoing in the Junior High Gymnasium and Board Office areas.
โ€ข Performing Arts Center perimeter and stage CMU walls have begun.

๐๐ฅ๐ฎ๐ฆ๐›๐ข๐ง๐ 
โ€ข Below-slab sanitary for the west locker room area is complete.
โ€ข Below-slab sanitary for the south locker room area is complete.
โ€ข Below-slab sanitary for โ€œArea 4โ€ Middle School is complete.
โ€ข Currently installing the underdrain piping on the north side of the Performing Arts Center.
โ€ข Currently installing the below-slab storm piping that services the building Courtyard.
โ€ข Currently installing the sanitary lines that service the Kitchen area.
โ€ข Currently laying out and roughing in In-Wall Drains for the mason.

๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ
โ€ข Below-slab and in-wall electrical conduits in the main electrical room are ongoing.
โ€ข Below-slab feeders and branch conduits from the main electrical room to various points on the project are ongoing.
โ€ข Below-slab and in-wall electrical conduits in the sub electrical rooms are ongoing.
โ€ข Working with the masons to install wall boxes and conduit as masonry walls go up.

ConstructionUpdate4.6.21

ConstructionUpdate4.6.21 1

๐๐ž๐š๐ฏ๐ž๐ซ ๐‚๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ข๐จ๐ง
โ€ข Early sitework carpenters finished the rough carpentry on the concession building roof, softball visitorโ€™s dugout, and started the baseball visitorโ€™s dugout.
โ€ข Building package contractors began mobilizing equipment and materials. Courtyard 8โ€ storm line has been installed and backfilled. Rebar deliveries took place for Areas 1-6.

๐‚๐ฅ๐ž๐ฏ๐ž๐ฅ๐š๐ง๐ ๐‚๐ž๐ฆ๐ž๐ง๐ญ
โ€ข Workers began excavation for the Performing Arts Centerโ€™s sloped floor slab.
โ€ข Excavation and installation of concrete footings has taken place for the stage and perimeter wall, Area 1 Music rooms and back-of-house.

๐’๐ฉ๐ž๐ž๐ฅ๐ฆ๐š๐ง ๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ
โ€ข Started excavation for primary underground electrical pathways from the new school transformer to the main electrical room.
โ€ข Layout of all underground conduit feeds from the main electrical room to various locations in the building has begun.

๐’๐ญ๐š๐ง๐๐š๐ซ๐ ๐๐ฅ๐ฎ๐ฆ๐›๐ข๐ง๐  & ๐‡๐ž๐š๐ญ๐ข๐ง๐ 
โ€ข Layout of the underground storm and sanitary lines has begun. 

Construction3.11.21 2
Construction3.11.21 1

๐๐ž๐š๐ฏ๐ž๐ซ ๐‚๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ข๐จ๐ง
โ€ข ๐’๐ข๐ญ๐ž๐ฐ๐จ๐ซ๐ค ๐‚๐ซ๐ž๐ฐ:
   โ€ข Completed the storm cleanouts at the building pad
   โ€ข Installed the stone construction access โ€œRing Roadโ€ around the new building pad
   โ€ข Continued the storm piping at the south access road
   โ€ข Worked with the Village Water Department and State Fire Marshall to flush & hydro test the new water supply line and fire lines for the building.
โ€ข ๐‚๐š๐ซ๐ฉ๐ž๐ง๐ญ๐ž๐ซ๐ฌ:
   โ€ข Framed & sheathed the roofs for both the home baseball dugout & home softball dugout
   โ€ข Set and braced the trusses and framed the north overhang for the concession building
๐•๐š๐ฅ๐ž๐ง๐ญ๐ข๐ง๐ž ๐Œ๐š๐ฌ๐จ๐ง๐ซ๐ฒ
โ€ข Completed the masonry for all 4 dugouts
โ€ข Completed the perimeter masonry for the concession building
๐‚๐š๐ซ๐ญ๐ž๐ซ ๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ
โ€ข Continued to work with Valentine Masonry to rough in conduits for power/lighting/fire/communication at the concession building
โ€ข Installed the buried power & technology conduits from the school transformer location to the concession transformer location
โ€ข Worked with AEP to get poles/power installed down Clever Lane to the school property
โ€ข Worked with AEP to pull primary wiring from Clever Lane to the school transformer & concession transformer locations
โ€ข Worked with AEP to set both the school & concessions transformers
โ€ข Worked with AEP to power up the new school transformer and electrical building utilizing the new primary service; The football complex is no longer powered from the school, it is now supported by the new AEP electrical service.

ConstructionUpdate2 4 21 2

ConstructionUpdate2 4 21 3

ConstructionUpdate2 4 21 1

โ€ข Masonry on 3 of the 4 dugouts is 100% complete.
โ€ข Work on the concessions building masonry has started.

Steel
โ€ข Installation of the steel columns and roof support beams for the dugouts has started.

Site Work
โ€ข The storm piping around the new school building pad is 100% complete.
โ€ข The water line and fire hydrant loop are 100% complete.
โ€ข Fire department connection is 100% complete.
โ€ข The 8โ€ fire & 4โ€ domestic water line to the school building perimeter is 100% complete.

Electrical
โ€ข Below grade conduit & duct-bank from Clever Lane, through the recently installed transformer vault, to the new Electrical Building is complete.
โ€ข Electrical Building: Installation of electrical transformers, troughs, tubs, panels and controllers is 100% complete and in service
โ€ข The football complex temporary electrical cut over was successfully completed. This cut over allowed us to demolish the existing electrical building.
โ€ข The electricians have been working with the masons placing electrical conduits and boxes in/through the new masonry walls.

Demolition
โ€ข Eslich Wrecking was back on site to finish the demolition scope of the project. The work performed was demolition of the original electrical building. The demolition scope is now 100% Complete.

ConstructionUpdate1 6 211

ConstructionUpdate1 6 212

ConstructionUpdate1 6 213

๐‚๐š๐ซ๐ญ๐ž๐ซ ๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ
โ€ข Has installed the Electrical Duct Bank from Clever Lane to the location of the new AEP Transformer.
โ€ข They have started the rough in of the Electrical Equipment in the new Electrical Building. The new equipment in this Electrical Building will service the Football Stadium, Maintenance Areas and Field House.
โ€ข Has installed the below slab conduits at the Concessions Building.
โ€ข Working with AEP to bring new Electrical Service Down Clever Lane to the School Property.
โ€ข Working with Valentine Masonry to Rough in Conduits in the Masonry Walls.

๐–๐ก๐ข๐ฌ๐ฅ๐ž๐ซ ๐๐ฅ๐ฎ๐ฆ๐›๐ข๐ง๐  & ๐‡๐ž๐š๐ญ๐ข๐ง๐ 
โ€ข Whisler has installed all of the below slab plumbing and irrigation lines in the Concession Building.

๐•๐š๐ฅ๐ž๐ง๐ญ๐ข๐ง๐ž ๐Œ๐š๐ฌ๐จ๐ง๐ซ๐ฒ
โ€ข Has laid up enough block to bring the Concessions Building 2 courses above grade
โ€ข Softball Visitor Dugout is 100% Complete
โ€ข Baseball Visitor Dugout is 100% Complete
โ€ข The Softball & Baseball Knee Walls are in progress
โ€ข The Baseball Home Dugout is in progress
โ€ข The Softball Home Dugout has 1 course of block laid and will continue this week.

๐๐ž๐š๐ฏ๐ž๐ซ ๐„๐ฑ๐œ๐š๐ฏ๐š๐ญ๐จ๐ซ๐ฌ
โ€ข Sanitary Line is 100%
โ€ข Storm Lines are approximately 80%
โ€ข New Water Line is approximately 55%
โ€ข New School Building Pad is to Grade

Construction12 11 203

Construction12 111

Construction12 11 202

โ€ข The footers and base for the new concession stand has been roughed in where the new athletic fields will be
โ€ข The headwall has been placed for the detention pond beneath the new athletic fields
โ€ข Clever Lane was closed on October 24th to allow for the new water tap that will feed the new facility. The water and electric lines are being run next to the school and back to the construction site.
โ€ข The metering vault for the water line has delivered and placed in the upper high school/senior parking lot.
โ€ข The sanitary manhole has been installed near 546 to tie into the main sanitary line.