July 2022 - Facilities Update
Carpentry
โข Music rooms casework installations completed
โข Music rooms acoustic wall panels completed
โข PAC stage flooring ongoing
โขPAC ceiling finishes ongoing
โข PAC acoustic wall panels ongoing
โข West locker rooms flooring and ceiling tile installations completed
โข Main Gymnasium flooring installation ongoing
โข Kitchen corridors and support spaces ceiling tile installation ongoing
โข High School & Junior High main entrance steel canopies completed
โข Board Office areas flooring installation completed
โข Board Office casework installation ongoing
โข Student dining area ceiling grid installation ongoing
โข JH locker rooms flooring and ceiling grid installations completed
โข Junior High first floor ceiling grid and tile completed
โข Junior High second floor flooring and ceiling tile installations completed
โข Junior High first floor flooring installation ongoing
โข High School first and second floors commons area flooring completed
โข Junior High first floor ceiling grid and MEP finishes completed
โข Junior High first floor ceiling tile installation completed
โข Junior High second floor ceiling tile installations completed
โข Junior High second floor flooring installation completed
โข Junior High first floor flooring installation ongoing
โข Junior High first floor casework installation ongoing
โข Junior High second floor casework installation ongoing
Misc. Finishes
โข Furniture deliveries ongoing
โข High School first floor classroom furniture setup completed
โข High School second floor classroom furniture set up completed
โข Kitchen equipment installations ongoing
Concrete & Courtyard area
โข Sitework concrete and pavement installations completed
โข Student courtyard decorative gravel installation completed
Mechanical, Plumbing & Electric
โข HVAC start-ups completed
โข Student dining areas above ceiling MEP rough-ins completed
June 2022 - Facilities Update
Carpentry
โข Student Courtyard Concrete Installation completed
โข Junior High Second Floor Ceiling Grid completed
โข High School First and Second Floor Casework Installations completed
โข Junior High First and Second Floor Ceiling Grid Installations completed
โข Kitchen/Serving Areas Ceiling Grid Installation completed
โข Kitchen/Serving Areas Ceiling Grid Installation completed
โข Music Rooms Casework Installations ongoing
โข PAC Ceiling Finishes ongoing
โข Music Rooms Acoustic Wall Panels ongoing
โข Junior High First Floor Ceiling Grid ongoing
โข Junior High Second Floor Ceiling Tile Installations ongoing
Misc. Finishes
โข Kitchen Serving Areas Epoxy Flooring Installation completed
โข Main Gymnasium Gym Equipment Installations completed
โข South Locker Rooms Flooring Installation completed
โข Kitchen Serving Areas Epoxy Flooring Installation completed
โข Main Gymnasium Gym Equipment Installations completed
โข Elevator and Wheelchair Lift Installations completed
โข Board of Education First and Second Floor Porcelain Tile at Bathrooms completed
โข Board of Education Office Areas Ceiling Grid and Tile Installations completed
โข Furniture Deliveries ongoing
โข PAC Stage Flooring ongoing
โข West Locker Rooms Flooring Installations ongoing
โข High School & Junior High Main Entrance Steel Canopies ongoing
โข High School First and Second Floors Commons Area Flooring ongoing
Concrete & Courtyard area
โข Student Dining Stairs Installation and Concrete Infill completed
โข Site Concrete sidewalks and pavement Installations ongoing
โข Student Courtyard Decorative Gravel Installation ongoing
Plumbing & Electric
โข Main Gymnasium Overhead MEP Installations completed
โข South and West Locker Rooms Plumbing Fixture Installations completed
โข Junior High First and Second Floor Above Ceiling MEP Rough Ins completed
โข Student Dining Areas Above Ceiling MEP Rough Ins ongoing
โข Junior High First Floor MEP Finishes ongoing
May 2022 - Facilities Update
Carpentry
โข Performing Arts Center (PAC) stage area rigging and equipment installation completed
โข Elevator installation ongoing
โข PAC back of house and music rooms ceiling grid completed
โข High School and Auxiliary locker rooms ceiling grid installations completed
โข High School main entrance exterior wall framing completed
โข Board Office and first floor ceiling grid installations completed
โข High School second floor drywall finishing completed
โข Junior High first floor hang drywall completed
โข Junior High first floor finish drywall completed
โข High School first floor ceiling grid completed
โข Junior High second floor ceiling grid completed
โข Junior High first floor ceiling grid completed
โข Kitchen/Serving areas ceiling grid installation ongoing
โข Junior High first and second floor ceiling grid installations ongoing
Misc. Finishes
โข High School second floor wall painting completed
โข Junior High first floor wall painting completed
โข Junior High locker rooms wall painting ongoing
โข High School first floor classroom flooring completed
โข Junior High gymnasium wood flooring installation ongoing
โข High School gymnasium equipment installations ongoing
โข Board Offices & High School first and second floor porcelain tile at bathrooms ongoing
โข Junior High first and second floor porcelain tile at bathrooms ongoing
Masonry/Concrete
โข Sitework concrete and pavement installations ongoing
โข Student courtyard concrete installation ongoing
โข High School entrance CMU veneer completed
โข Junior High exterior CMU veneer completed
Plumbing & Electric
โข Kitchen fume hoods and ductwork installations completed
โข Junior High first and second floor above ceiling MEP rough-ins ongoing
February 2022 - Facilities Update
Masonry
โข Courtyard CMU veneer is complete
โข High School CMU veneer is ongoing
โข Junior High second floor interior CMU wall construction is ongoing
Structural Steel
โข High School Gym mezzanine stairs are complete
Roofing
โข High School roofing system installation is complete
โข Board Offices & Student Dining high and low roof system installations are complete
Plumbing & Electric
โข High School in-wall and overhead MEP (Mechanical Electrical Plumbing) rough-ins are complete
โข High School second floor fire suppression piping rough-in is complete
โข High School second floor MEP overhead rough-in is complete
โข High School first and second floor overhead and in-wall MEP rough-ins are complete
โข High School gymnasium overhead MEP installations are complete
โข Junior High overhead MEP rough-in is ongoing
โข Junior High gymnasium overhead MEP rough-ins are ongoing
โข Auxiliary gymnasium overhead MEP installations are ongoing
Carpentry
โข Performing Arts Center partition wall framing is ongoing
โข Music rooms door and window installations are complete
โข Music rooms first and second coats of paint on walls is complete
โข Kitchen/Serving areas first and second coats of wall paint are complete
โข Main Gymnasium first coat of paint on walls is complete
โข Junior High first and second floor window unit installations are ongoing
โข Junior High first and second floor interior wall framing is complete
โข High School second floor insulation and drywall installations are complete
โข High School first floor insulation and drywall installations are complete
โข High School first and second floor window unit installations are complete
โข High School second floor prime walls and first coat of paint are complete
โข Junior High first and second floor window unit installation is ongoing
โข Junior High first and second floors insulation and drywall Installation are ongoing
January 2022 - Facilities Update
Concrete
โข Junior High second story concrete floor pour is complete
Masonry
โข Junior High east wall CMU veneer is complete
โข Junior High second floor interior CMU wall construction ongoing
โข High School and Junior High east wall brick veneer ongoing
Structural Steel
โข Student Dining Area structural steel installation is complete
โข Student Dining Area structural steel and decking installations is complete
Roofing
โข Music Rooms roof detailing is complete
โข Junior High roof detailing is complete
โข Junior High Gymnasium roof detailing is complete
โข High School Gymnasium roof detailing is complete
โข Auxiliary Gymnasium roof detailing is complete
โข Junior High roofing system installation ongoing
โข Board Offices high and low roof system installations ongoing
Plumbing & Electric
โข Gas service to the building is complete
โข High School first and second floor in-wall mechanical, electrical, and plumbing (MEP) rough-ins are complete
โข High School first and second floor overhead and in-wall MEP rough-ins ongoing
โข Junior High Air Handling Unit installations are complete
โข Rooftop HVAC unit installations are complete
โข Electric service to the building is complete
โข Junior High in-wall and overhead MEP rough-ins ongoing
โข Junior High gymnasium overhead MEP rough-ins ongoing
โข Main gymnasium overhead MEP installations ongoing
โข Auxiliary gymnasium overhead MEP installations ongoing
Carpentry
โข Junior High window installations is complete
โข Junior High exterior wall framing is complete
โข High School second floor insulation and drywall installations ongoing
โข Music rooms doors and windows installations ongoing
โข Performing Arts Center partition wall framing ongoing
December 3, 2021
Early Site Package:
โข ADA ramp to baseball field concrete work was completed
โข Baseball field sod placement is nearing completion
โข Bleachers & press boxes were completed for both the softball and baseball fields
โข The asphalt drive to the baseball field was completed
โข The cubbies in all dugouts were completed
โข The net systems for the batting cages was completed
โข Final grade and seed are in progress
Building Package:
Masonry
โข Courtyard CMU veneer is complete
โข Performing Arts Center seating area interior CMU walls is complete
โข Music Rooms non-bearing interior CMU walls is complete
โข South Locker Rooms non-bearing interior CMU walls is complete
โข West Locker Rooms non-bearing interior CMU walls is complete
โข High School (HS) north wall CMU veneer ongoing
โข Junior High (JH) east wall CMU veneer ongoing
Structural Steel
โข JH structural steel and decking installations are complete
โข Dining area structural steel installation ongoing
Roofing
โข HS roofing system installation is complete
โข Music Rooms roofing system installation is complete
โข Main Gym/North and South Mezzanines roofing system installation is complete
โข JH Gym roofing system installation is complete
โข Auxiliary Gym roofing system installation is complete
โข Main Mechanical and Electrical Rooms roofing system installation is complete
โข Area 3 roofing system installation ongoing
Plumbing & Electric
โข JH above ceiling mechanical, electrical, and plumbing (MEP) rough-ins at first and second floors are complete
โข Main Gym Overhead MEP rough-ins ongoing
โข JH first and second floor overhead MEP rough-ins ongoing
โข JH first and second floor in wall MEP rough-ins ongoing
โข HS first and second floor in wall MEP rough-ins ongoing
Carpentry
โข HS interior wall framing at first and second floors is complete
โข HS exterior wall framing is complete
โข HS and JH window system installations ongoing
November 3, 2021
Early Site Package:
โข Baseball and softball press boxes installed
โข Baseball and softball bleachers installed
โข Sod placed at softball field
โข Baseball and softball fence pads installed
โข Baseball and softball dugout benches and storage cubbies installed
โข ADA ramp and steps continues
โข Site concrete continues
Building Package:
Concrete
โข Auxiliary gymnasium concrete slab-on-grade is complete
โข Junior High area slab-on-deck concrete pour is complete
โข Mechanical courtyard concrete construction is complete
Masonry
โข Auxiliary gymnasium CMU is complete
โข West Locker Rooms interior CMU walls are complete
โข Music Rooms/BOH CMU and veneer installations is complete
โข High School courtyard CMU veneer is complete
โข Junior High CMU walls at first floor is complete
โข High School north wall CMU veneer is ongoing
โข PAC (Performing Arts Center) seating area interior CMU walls is ongoing
Structural Steel
โข Music Rooms structural steel installations is complete
โข Roof Decking at all gymnasiums is complete
Roofing
โข Main gymnasium roofing system is complete
โข PAC seating area roofing system is complete
โข High School roofing system installation is ongoing
โข Junior High roofing system installation is ongoing
โข Music Rooms roofing system installation is ongoing
โข Main Mechanical and Electrical rooms roofing systems are complete
Plumbing & Electric
โข High School above ceiling MEP rough-ins is complete
โข Junior High above ceiling MEP rough ins at first and second floors is ongoing
Carpentry
โข Junior High interior wall framing at first and second floors is ongoing
โข High School exterior and interior wall framing is complete
โข Junior High exterior wall framing is complete
October 6, 2021
Early Site Package:
Baseball & Softball Fields
โข Foul ball poles have been installed on both fields
โข Scoreboards for both fields have been installed
โข Benches in the dugouts are currently being installed
โข Both fields have been prepped and for sod
โข Sod installation began week of 9/27
โข Irrigation systems will be final tested this week
โข Press boxes have been delivered
ADA Access Ramp
โข The ADA Ramp is progressing. Beaver continues to form and pour sections of the walls. Once the walls are done they will start the stair sections and slabs on grade.
Building Package:
Concrete
โข Area 5 second floor concrete slab placement completed
โข JH gymnasium concrete slab on grade placement completed
โข Main gymnasium concrete slab on grade placement completed
Masonry
โข Main gymnasium CMU veneer at exterior walls completed
โข JH gymnasium CMU veneer at exterior walls completed
โข Music rooms CMU and brick veneer installations ongoing
Structural Steel
โข In-wall MEP rough-in at Area 3 board office partition walls completed
โข Area 5 structural steel and decking installation completed
โข Area 6 structural steel installation completed
โข JH gymnasium steel bar joist installations completed
โข Main gymnasium steel bar joist installations completed
โข Auxiliary gymnasium steel bar joist installations completed
โข Main mechanical and main electrical rooms steel bar joist and decking installations completed
โข Area 6 structural roof decking installations ongoing
โข Main gym/JH gym/Auxiliary gym structural roof decking installations ongoing
โข Music rooms structural steel roof bar joist and roof decking installations
Roofing
โข West locker rooms roof system installation completed
โข Performing Arts Center stage area roof system installation completed
โข Performing Arts Center seating area roof system installation completed
Plumbing & Electric
โข South Locker Rooms above-ceiling MEP rough-in completed
โข Kitchen and Serving Areas above ceiling MEP installations ongoing
โข Area 3 above ceiling MEP rough ins ongoing
โข Area 5 above ceiling MEP rough ins ongoing
Carpentry
โข Exterior and interior wall framing at Area 3 board offices completed
โข Area 5 interior and exterior wall framing ongoing
August 23, 2021 Update
๐๐๐ซ๐ฅ๐ฒ ๐๐ข๐ญ๐ ๐๐๐๐ค๐๐ ๐
๐๐จ๐๐ญ๐๐๐ฅ๐ฅ & ๐๐๐ฌ๐๐๐๐ฅ๐ฅ ๐
๐ข๐๐ฅ๐๐ฌ
โข Concrete placed for batting cages
โข Concrete placed for bleachers and press boxes
โข Placement of ballfield mix
โข Field irrigation system
โข Outfield fencing
๐๐จ๐ง๐๐๐ฌ๐ฌ๐ข๐จ๐ง ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐
โข Concrete placed for sidewalks and concession stand aprons
๐๐ข๐ญ๐ ๐๐จ๐ซ๐ค
โข Topsoil and hydroseed placed at hillsides and soccer practice fields
โข Installation of ADA ramps and stairs at hillside
๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ ๐๐๐๐ค๐๐ ๐
๐๐จ๐ง๐๐ซ๐๐ญ๐
โข Completed Kitchen and Main Mechanical Rooms concrete slab on grade
โข Prep for and place concrete slab on deck at Main Gymnasium south mezzanine completed
โข Place concrete slab on grade at Area 4 J.H. locker areas and student areas completed
โข Prep and place concrete stairs at PAC stage right and stage left ongoing
๐๐๐ฌ๐จ๐ง๐ซ๐ฒ
โข CMU walls at Kitchen and Main Mechanical Rooms completed
โข CMU veneer at Auxiliary gymnasium east wall completed
โข CMU at Auxiliary Gymnasium north and east walls completed
โข CMU walls at Auxiliary Gymnasium West Locker Rooms completed
โข CMU walls at South Locker Rooms completed
โข CMU walls at Area One Music Rooms and Back of House areas ongoing
โข CMU at JH gymnasium west and south walls ongoing
๐๐ญ๐ซ๐ฎ๐๐ญ๐ฎ๐ซ๐๐ฅ ๐๐ญ๐๐๐ฅ
โข Structural steel erection at Main Gymnasium south mezzanine completed
โข Structural steel erection at Area 3 Administration and Special Ed first and second floors completed
โข Main gymnasium north mezzanine structural steel and decking installations ongoing
๐๐ฅ๐ฎ๐ฆ๐๐ข๐ง๐ & ๐๐ฅ๐๐๐ญ๐ซ๐ข๐
โข MEP under slab installation at Area 4 J.H. locker areas and student areas completed
โข MEP under slab installations at PAC stage area ongoing
๐๐๐ซ๐ฉ๐๐ง๐ญ๐ซ๐ฒ
โข Installation of treated lumber cap at PAC and Stage roof parapet walls ongoing
June 14, 2021 Update
๐๐๐ซ๐ฅ๐ฒ ๐๐ข๐ญ๐ ๐๐๐๐ค๐๐ ๐
๐๐จ๐ง๐๐๐ฌ๐ฌ๐ข๐จ๐ง๐ฌ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐
โข Above ceiling electrical rough-in has been completed.
โข The electrical room panels and transformer have been installed and wired.
โข Lighting suspended in the acoustic grid and has been installed.
โข Above ceiling mechanical has been completed.
โข Toilet chase rough-in and above ceiling rough-in has been completed.
โข Interior walls have been cleaned and painted.
โข Drywall ceilings have been hung.
โข Acoustical ceiling grid has been laid out and installed.
โข Concrete frost slabs have been poured.
โข Irrigation system supply piping is being installed.
๐๐ฎ๐ ๐จ๐ฎ๐ญ๐ฌ
โข Metal roofing, trim & downspouts are nearing completion.
โข Masonry has been painted.
โข Concrete slabs/frost slabs have been poured.
โข Doors and hardware have been installed.
๐๐ฅ๐๐๐ญ๐ซ๐ข๐๐๐ฅ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐
โข Metal roofing, trim & downspout are nearing completion.
โข Concrete frost slab was poured.
โข Door opening is being prepped for door and hardware placement.
๐๐ข๐ญ๐๐ฐ๐จ๐ซ๐ค
โข All storm piping has been completed.
โข Storm structure inverts have been poured.
โข The Bio-Retention pond at 546 has been excavated and media has been placed.
โข Fine grade and topsoil have been placed on the south side of the property, around the detention pond and on the majority of the soccer fields.
โข Grass seed is placed on the south side of the property and around the detention pond. Seed placement will continue north towards the new school building.
โข The fire lane on the east side of the new school has been cut to grade and stoned.
โข Installation of site conduits from the concession building to the dugouts, scoreboards, and future ball field lighting is in progress.
๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ ๐๐๐๐ค๐๐ ๐
๐๐จ๐ง๐๐ซ๐๐ญ๐
โข Elevator shaft foundations/pit slab and pit walls are complete.
โข SOG prep and pour at Area 3 (admin) area is ongoing.
โข SOG prep at Area 5 (high school academic) area is ongoing.
๐๐๐ฌ๐จ๐ง๐ซ๐ฒ
โข CMU at PAC/stage north and west walls are complete.
โข CMU from top of footing to FF elevation at entire perimeter of building is complete.
โข Structural steel column base plates and grout is complete.
โข CMU to roof height at Area 2 main electrical room is complete.
โข Masonry veneer at PAC/stage north and west walls is ongoing.
โข CMU at PAC/stage south wall is ongoing.
โข CMU at main gymnasium walls is ongoing.
โข CMU at JH gymnasium north and east walls is ongoing.
๐๐ฅ๐ฎ๐ฆ๐๐ข๐ง๐
โข Standard Plumbing has continued with the below slab installation of the sanitary lines, storm lines and acid waste lines in the Administration area, the kitchen, and education areas.
โข Standard Plumbing has been working with Valentine Masonry coordinating all wall sleeves for future pipe installations and all wall openings for future duct installation.
๐๐ฅ๐๐๐ญ๐ซ๐ข๐
โข Speelman Electric has continued with the below slab installation of the feeder conduits from the main electrical rooms to sub locations and then all of the branch circuits for distribution.
โข Speelman Electric has been working with Valentine Masonry coordinating all of the in- wall conduits for lighting, power, equipment, etc. as required.
โข Speelman Electric has excavated, placed and backfilled site electrical conduits from the main building down the access road to Route 546. They have placed the light pole bases down the access road to Route 546.
May 6, 2021 Update
๐๐จ๐ง๐๐๐ฌ๐ฌ๐ข๐จ๐ง๐ฌ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐
๐๐ฅ๐๐๐ญ๐ซ๐ข๐๐๐ฅ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐
๐๐ข๐ญ๐๐ฐ๐จ๐ซ๐ค
๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ ๐๐๐๐ค๐๐ ๐
๐๐จ๐ง๐๐ซ๐๐ญ๐


April 6, 2021 Update
๐๐๐ซ๐ฅ๐ฒ ๐๐ข๐ญ๐ ๐๐๐๐ค๐๐ ๐
๐๐จ๐ง๐๐๐ฌ๐ฌ๐ข๐จ๐ง๐ฌ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐
โข Beaver Construction has formed and poured the slab on grade.
โข The Valentine Masonry, with assistance from the electricians and plumbing contractor, have installed the interior CMU Walls.
โข Valentine Masonry has caulked all of the interior masonry control joints in preparation of interior painting.
โข The Whisler Plumbing Contractor has roughed in all sanitary & domestic lines required in the mechanical chase and concessions area.
โข Advance Roofing has installed the asphalt shingles.
โข Carter Electric has installed the AEP Metering System.
โข Carter Electric has excavated and placed all power & technology conduits from AEP.
๐๐ฅ๐๐๐ญ๐ซ๐ข๐ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐
โข Advance Roofing has installed the metal roofing system.
โข Valentine Masonry has caulked all of the interior masonry control joints.
๐๐ฎ๐ ๐จ๐ฎ๐ญ๐ฌ
โข Beaver Construction for all 4 dugouts has formed the slabs for the concrete floors.
โข Valentine Masonry has caulked all of the interior masonry control joints in preparation of interior painting.
๐๐จ๐๐ญ๐๐๐ฅ๐ฅ ๐
๐ข๐๐ฅ๐
โข Valentine Masonry has completed the knee wall between the dugouts.
๐๐๐ฌ๐๐๐๐ฅ๐ฅ ๐
๐ข๐๐ฅ๐
โข Valentine Masonry has completed the knee wall between the dugouts.
๐-๐๐ ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ ๐๐๐๐ค๐๐ ๐
๐๐จ๐ง๐๐ซ๐๐ญ๐
โข All concrete foundations are now in place.
โข Elevator shaft construction has begun.
โข Backfill of footing ditches at Performing Arts Center (PAC) is ongoing.
๐๐๐ฌ๐จ๐ง๐ซ๐ฒ
โข CMU from top of footing to finish floor elevation is complete at the following areas:
โข High School gymnasium perimeter
โข High School gymnasium south locker room
โข Auxiliary gymnasium perimeter
โข Auxiliary gymnasium west locker room
โข PAC walls and stage
โข Music rooms
โข Junior High gymnasium
โข CMU from top of footing to finish floor is ongoing in the Junior High Gymnasium and Board Office areas.
โข Performing Arts Center perimeter and stage CMU walls have begun.
๐๐ฅ๐ฎ๐ฆ๐๐ข๐ง๐
โข Below-slab sanitary for the west locker room area is complete.
โข Below-slab sanitary for the south locker room area is complete.
โข Below-slab sanitary for โArea 4โ Middle School is complete.
โข Currently installing the underdrain piping on the north side of the Performing Arts Center.
โข Currently installing the below-slab storm piping that services the building Courtyard.
โข Currently installing the sanitary lines that service the Kitchen area.
โข Currently laying out and roughing in In-Wall Drains for the mason.
๐๐ฅ๐๐๐ญ๐ซ๐ข๐
โข Below-slab and in-wall electrical conduits in the main electrical room are ongoing.
โข Below-slab feeders and branch conduits from the main electrical room to various points on the project are ongoing.
โข Below-slab and in-wall electrical conduits in the sub electrical rooms are ongoing.
โข Working with the masons to install wall boxes and conduit as masonry walls go up.
March 11, 2021 Update
๐๐๐๐ฏ๐๐ซ ๐๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ข๐จ๐ง
โข Early sitework carpenters finished the rough carpentry on the concession building roof, softball visitorโs dugout, and started the baseball visitorโs dugout.
โข Building package contractors began mobilizing equipment and materials. Courtyard 8โ storm line has been installed and backfilled. Rebar deliveries took place for Areas 1-6.
๐๐ฅ๐๐ฏ๐๐ฅ๐๐ง๐ ๐๐๐ฆ๐๐ง๐ญ
โข Workers began excavation for the Performing Arts Centerโs sloped floor slab.
โข Excavation and installation of concrete footings has taken place for the stage and perimeter wall, Area 1 Music rooms and back-of-house.
๐๐ฉ๐๐๐ฅ๐ฆ๐๐ง ๐๐ฅ๐๐๐ญ๐ซ๐ข๐
โข Started excavation for primary underground electrical pathways from the new school transformer to the main electrical room.
โข Layout of all underground conduit feeds from the main electrical room to various locations in the building has begun.
๐๐ญ๐๐ง๐๐๐ซ๐ ๐๐ฅ๐ฎ๐ฆ๐๐ข๐ง๐ & ๐๐๐๐ญ๐ข๐ง๐
โข Layout of the underground storm and sanitary lines has begun.


February 4, 2021 Update
๐๐๐๐ฏ๐๐ซ ๐๐จ๐ง๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ข๐จ๐ง
โข ๐๐ข๐ญ๐๐ฐ๐จ๐ซ๐ค ๐๐ซ๐๐ฐ:
โข Completed the storm cleanouts at the building pad
โข Installed the stone construction access โRing Roadโ around the new building pad
โข Continued the storm piping at the south access road
โข Worked with the Village Water Department and State Fire Marshall to flush & hydro test the new water supply line and fire lines for the building.
โข ๐๐๐ซ๐ฉ๐๐ง๐ญ๐๐ซ๐ฌ:
โข Framed & sheathed the roofs for both the home baseball dugout & home softball dugout
โข Set and braced the trusses and framed the north overhang for the concession building
๐๐๐ฅ๐๐ง๐ญ๐ข๐ง๐ ๐๐๐ฌ๐จ๐ง๐ซ๐ฒ
โข Completed the masonry for all 4 dugouts
โข Completed the perimeter masonry for the concession building
๐๐๐ซ๐ญ๐๐ซ ๐๐ฅ๐๐๐ญ๐ซ๐ข๐
โข Continued to work with Valentine Masonry to rough in conduits for power/lighting/fire/communication at the concession building
โข Installed the buried power & technology conduits from the school transformer location to the concession transformer location
โข Worked with AEP to get poles/power installed down Clever Lane to the school property
โข Worked with AEP to pull primary wiring from Clever Lane to the school transformer & concession transformer locations
โข Worked with AEP to set both the school & concessions transformers
โข Worked with AEP to power up the new school transformer and electrical building utilizing the new primary service; The football complex is no longer powered from the school, it is now supported by the new AEP electrical service.
January 6, 2021 Update
โข Masonry on 3 of the 4 dugouts is 100% complete.
โข Work on the concessions building masonry has started.
Steel
โข Installation of the steel columns and roof support beams for the dugouts has started.
Site Work
โข The storm piping around the new school building pad is 100% complete.
โข The water line and fire hydrant loop are 100% complete.
โข Fire department connection is 100% complete.
โข The 8โ fire & 4โ domestic water line to the school building perimeter is 100% complete.
Electrical
โข Below grade conduit & duct-bank from Clever Lane, through the recently installed transformer vault, to the new Electrical Building is complete.
โข Electrical Building: Installation of electrical transformers, troughs, tubs, panels and controllers is 100% complete and in service
โข The football complex temporary electrical cut over was successfully completed. This cut over allowed us to demolish the existing electrical building.
โข The electricians have been working with the masons placing electrical conduits and boxes in/through the new masonry walls.
Demolition
โข Eslich Wrecking was back on site to finish the demolition scope of the project. The work performed was demolition of the original electrical building. The demolition scope is now 100% Complete.
December 11, 2020 Update
๐๐๐ซ๐ญ๐๐ซ ๐๐ฅ๐๐๐ญ๐ซ๐ข๐
โข Has installed the Electrical Duct Bank from Clever Lane to the location of the new AEP Transformer.
โข They have started the rough in of the Electrical Equipment in the new Electrical Building. The new equipment in this Electrical Building will service the Football Stadium, Maintenance Areas and Field House.
โข Has installed the below slab conduits at the Concessions Building.
โข Working with AEP to bring new Electrical Service Down Clever Lane to the School Property.
โข Working with Valentine Masonry to Rough in Conduits in the Masonry Walls.
๐๐ก๐ข๐ฌ๐ฅ๐๐ซ ๐๐ฅ๐ฎ๐ฆ๐๐ข๐ง๐ & ๐๐๐๐ญ๐ข๐ง๐
โข Whisler has installed all of the below slab plumbing and irrigation lines in the Concession Building.
๐๐๐ฅ๐๐ง๐ญ๐ข๐ง๐ ๐๐๐ฌ๐จ๐ง๐ซ๐ฒ
โข Has laid up enough block to bring the Concessions Building 2 courses above grade
โข Softball Visitor Dugout is 100% Complete
โข Baseball Visitor Dugout is 100% Complete
โข The Softball & Baseball Knee Walls are in progress
โข The Baseball Home Dugout is in progress
โข The Softball Home Dugout has 1 course of block laid and will continue this week.
๐๐๐๐ฏ๐๐ซ ๐๐ฑ๐๐๐ฏ๐๐ญ๐จ๐ซ๐ฌ
โข Sanitary Line is 100%
โข Storm Lines are approximately 80%
โข New Water Line is approximately 55%
โข New School Building Pad is to Grade
October 30, 2020 Update
โข The footers and base for the new concession stand has been roughed in where the new athletic fields will be
โข The headwall has been placed for the detention pond beneath the new athletic fields
โข Clever Lane was closed on October 24th to allow for the new water tap that will feed the new facility. The water and electric lines are being run next to the school and back to the construction site.
โข The metering vault for the water line has delivered and placed in the upper high school/senior parking lot.
โข The sanitary manhole has been installed near 546 to tie into the main sanitary line.