• Masonry on 3 of the 4 dugouts is 100% complete.
• Work on the concessions building masonry has started.

Steel
• Installation of the steel columns and roof support beams for the dugouts has started.

Site Work
• The storm piping around the new school building pad is 100% complete.
• The water line and fire hydrant loop are 100% complete.
• Fire department connection is 100% complete.
• The 8” fire & 4” domestic water line to the school building perimeter is 100% complete.

Electrical
• Below grade conduit & duct-bank from Clever Lane, through the recently installed transformer vault, to the new Electrical Building is complete.
• Electrical Building: Installation of electrical transformers, troughs, tubs, panels and controllers is 100% complete and in service
• The football complex temporary electrical cut over was successfully completed. This cut over allowed us to demolish the existing electrical building.
• The electricians have been working with the masons placing electrical conduits and boxes in/through the new masonry walls.

Demolition
• Eslich Wrecking was back on site to finish the demolition scope of the project. The work performed was demolition of the original electrical building. The demolition scope is now 100% Complete.

ConstructionUpdate1 6 211

ConstructionUpdate1 6 212

ConstructionUpdate1 6 213

𝐂𝐚𝐫𝐭𝐞𝐫 𝐄𝐥𝐞𝐜𝐭𝐫𝐢𝐜
• Has installed the Electrical Duct Bank from Clever Lane to the location of the new AEP Transformer.
• They have started the rough in of the Electrical Equipment in the new Electrical Building. The new equipment in this Electrical Building will service the Football Stadium, Maintenance Areas and Field House.
• Has installed the below slab conduits at the Concessions Building.
• Working with AEP to bring new Electrical Service Down Clever Lane to the School Property.
• Working with Valentine Masonry to Rough in Conduits in the Masonry Walls.

𝐖𝐡𝐢𝐬𝐥𝐞𝐫 𝐏𝐥𝐮𝐦𝐛𝐢𝐧𝐠 & 𝐇𝐞𝐚𝐭𝐢𝐧𝐠
• Whisler has installed all of the below slab plumbing and irrigation lines in the Concession Building.

𝐕𝐚𝐥𝐞𝐧𝐭𝐢𝐧𝐞 𝐌𝐚𝐬𝐨𝐧𝐫𝐲
• Has laid up enough block to bring the Concessions Building 2 courses above grade
• Softball Visitor Dugout is 100% Complete
• Baseball Visitor Dugout is 100% Complete
• The Softball & Baseball Knee Walls are in progress
• The Baseball Home Dugout is in progress
• The Softball Home Dugout has 1 course of block laid and will continue this week.

𝐁𝐞𝐚𝐯𝐞𝐫 𝐄𝐱𝐜𝐚𝐯𝐚𝐭𝐨𝐫𝐬
• Sanitary Line is 100%
• Storm Lines are approximately 80%
• New Water Line is approximately 55%
• New School Building Pad is to Grade

Construction12 11 203

Construction12 111

Construction12 11 202

• The footers and base for the new concession stand has been roughed in where the new athletic fields will be
• The headwall has been placed for the detention pond beneath the new athletic fields
• Clever Lane was closed on October 24th to allow for the new water tap that will feed the new facility. The water and electric lines are being run next to the school and back to the construction site.
• The metering vault for the water line has delivered and placed in the upper high school/senior parking lot.
• The sanitary manhole has been installed near 546 to tie into the main sanitary line.

FacilitiesUpdate10 30 20